Maintenance intervals in a training fleet: why the 100-hour check always lands in the wrong week
A training aircraft flying 80 hours a month reaches its 100-hour check every five weeks. Maintenance comes as a surprise not because the interval is short, but because the hours remaining are not on the scheduling screen.
- Published
- 5 min read
- 5 min read
- By
- ATO Planner
A privately used aircraft flies somewhere between 50 and 100 hours a year, and the calendar decides its maintenance. A training aircraft is the opposite: at 80 hours a month it uses up a 100-hour interval in five weeks. Each aircraft goes into maintenance ten times a year and comes off the schedule every time. In many schools, maintenance is still announced with the sentence “the aircraft is not available tomorrow”.
Where the interval comes from
The interval is set by the aircraft’s approved maintenance programme. On the EASA side, Part-ML, which covers light aircraft, defines the interval for aeroplanes in its minimum inspection programme as annual or 100 hours, whichever comes first. Manufacturer programmes usually add 50-hour checks in between.
The same provision allows a tolerance of 1 month or 10 hours on that interval, with one condition: the next interval is calculated from the date and hours at which the inspection actually took place.
Why the tolerance is not a reserve
A school that treats the tolerance as part of the plan loses two things.
No hours are gained. Because the next interval runs from the moment the inspection is done, the tolerance does not move the calendar forward; it only rescues that one week. A school that takes every inspection at the end of the tolerance goes into maintenance exactly as often as a school with no tolerance, with one difference: it has no margin left for the week it is squeezed.
At the annual, another date comes into play. EASA’s acceptable means of compliance warn explicitly that using the 1-month tolerance for the annual inspection may result in an expired airworthiness review certificate (ARC). A maintenance tolerance does not extend the certificate.
The rule is not the same everywhere either. In the United States the 100-hour limit may be exceeded by no more than 10 hours, and only while en route to the place of inspection; the excess is deducted from the next 100 hours. Which rule applies depends on the aircraft’s registration and maintenance programme.
Two clocks run at once
In a training fleet, flight hours usually trigger maintenance, but the calendar keeps running too. An aircraft that flies little in winter, or sits on the ground for weeks with a defect, reaches its annual before it reaches 100 hours. Other limits need tracking alongside: engine and propeller life, ARC expiry, insurance, repetitive airworthiness directives.
Each of these counts in a different unit: hours, cycles or a date. A single “next maintenance” cell cannot hold them all.
The four scheduling mistakes we see most
1. Hours remaining live only in the technical log
The hours remaining are written correctly in the technical records, but the person building the schedule does not look there. The aircraft gets a full week of flights, the hours run out on Wednesday, and Thursday’s and Friday’s flights are cancelled. The information existed; it was on the wrong screen.
2. Scheduling a flight longer than the hours remaining
An aircraft with 2.5 hours to its check is given a 3-hour cross-country. A margin that is enough for circuits is not enough for a navigation flight. The check has to compare the planned duration of the flight with the hours remaining, not just ask whether the aircraft is in maintenance.
3. The whole fleet falling due in the same week
Aircraft bought in the same period and flown at similar rates come due in the same week. For a four-aircraft school, that means a week at half capacity.
4. Not being clear about which meter counts
An aircraft has more than one meter, and they show different values for the same flight. Records should be kept on whichever one the maintenance programme is based on. If the team does not know that the time billed to the student and the time counted towards maintenance need not be the same, the two numbers get mixed up.
Staggering: the arithmetic is simple
Four aircraft at 80 hours a month fly 320 hours a month between them. That is more than three 100-hour checks a month, or roughly one every nine days. The question is not whether maintenance is coming, but which aircraft goes in during which nine days.
The tool for staggering is aircraft assignment. Giving long exercises to the aircraft closest to its check and short ones to the aircraft furthest from it widens the gap between them. For that, the scheduler has to see each aircraft’s hours remaining while assigning the flight. Booking the maintenance slot in advance, from a date projected out of the hours remaining and the weekly flying average instead of waiting for the hours to run out, comes from the same table.
What should be on the screen
- Each aircraft’s current meter reading and hours to maintenance, on the screen where scheduling is done
- The inspection type (50-hour, 100-hour, annual) and the calendar limit side by side
- Separate rows for engine, propeller, ARC and insurance
- A projected maintenance date based on the flying average of recent weeks
- A warning at save time when a planned flight is longer than the hours remaining
If hours to maintenance drop by themselves with every completed flight, this table stays current. A table updated by hand goes stale in the week it is needed most, which is the week with the most flying.
This article is general information. What binds you is your aircraft’s approved maintenance programme and the continuing airworthiness rules of your registration authority.